Where Wardrobes Sit in a New Build Sequence

Where Wardrobes Sit in a New Build Sequence

Wardrobes go in near the end. The walls have to be lined, set and painted, the room has to be at its final dimensions, and any electrical work on the wardrobe wall has to be done. Joinery is then measured against the finished room, manufactured, and installed, usually before carpet and often after hard flooring. The decisions, though, have to be made much earlier than the installation, and that gap between deciding and installing is where most of the problems on a new build come from.

This guide sets out the sequence, who is responsible for what, and the points at which a decision made too late costs money.

Who this is for

Three audiences, with different versions of the same problem.

Owners building a new home. You are choosing between the builder’s standard inclusion, an upgrade through the builder, and a separate contract with a joinery company after handover. The decision has timing consequences you may not have been told about.

Builders and project managers. You are sequencing a trade into a program where the preceding trades will not all finish on time and the joinery cannot be remeasured indefinitely.

Developers on multi-unit projects. Same as above, at a scale where a measurement assumption applied across forty apartments is either forty correct wardrobes or forty wrong ones.

The sequence below applies to all three. The commercial arrangements differ.

The sequence, in order

1. Design and documentation. Wardrobe locations, sizes and door swings appear on the plans. This is the moment to question whether the nominated wardrobe actually suits how the room will be used, because everything downstream assumes these positions.

2. Structural work and lock-up. Frame, roof, windows, external doors. Nothing joinery-related happens yet, but the wall positions become real here and they are not always exactly where the plan put them.

3. Rough-in. Electrical, plumbing and data run through the frame. This is the critical moment for wardrobes and it happens long before anyone thinks about wardrobes. If you want internal wardrobe lighting, a power point inside a cupboard, or a data point in a home office joinery run, the cable goes in now. After the walls are lined it is a far messier job.

It is also the moment to move a light switch or a power point off the wardrobe wall, rather than building around it later.

4. Lining, setting and cornice. The walls become their finished thickness. Only now is a wall measurement meaningful. Measuring to a frame or to unset plasterboard produces a wardrobe that does not fit.

5. Painting. Walls are painted before the joinery goes in, not after. Painting around installed joinery is slow, produces a worse result, and risks the finish on the doors.

6. Hard flooring, if applicable. Timber, tile and vinyl are usually laid before joinery, so the joinery sits on the finished floor. This is a decision rather than a rule, and it needs to be made explicitly.

7. Check measure. A final measurement of the actual finished room. Covered in detail below.

8. Manufacture.

9. Joinery installation. Wardrobes, home office joinery, linen cupboards.

10. Carpet. Usually laid after joinery, so it runs up to the unit rather than under it. The alternative, carpet under the wardrobe, wastes carpet and is harder to replace later.

11. Handover and defects. Covered below.

When do the decisions have to be made?

Earlier than the installation, and this is the point of the article.

Decision

Must be made by

Whether there is wardrobe lighting, and where

Before rough-in

Power or data inside the joinery

Before rough-in

Moving a switch or outlet off the wardrobe wall

Before rough-in

Whether the wardrobe runs to the ceiling

Before lining, since a bulkhead or set-down changes it

Door type, hinged or sliding

Before manufacture, and it affects floor finish decisions

Internal layout

Before manufacture

Finish and colour

Before manufacture

Whether hard flooring runs under the unit

Before flooring

Carpet before or after

Before joinery installation

Rough-in is the deadline people miss, because it happens while the house still looks like a frame and nobody is thinking about wardrobe interiors yet.

What is a check measure, and when should it happen?

A check measure is a final measurement taken once the room is in its finished state: walls lined, set and painted, hard flooring down if it is going down first, and nothing else due to change.

It matters because the difference between a plan dimension and a built dimension is routinely enough to matter over a wardrobe-length run. Frames move, linings vary, sets vary, and walls are rarely exactly where the drawing said.

Three things to get right:

Timing. Too early and you are measuring an unfinished room. Too late and the manufacturing time pushes the installation past the program. A check measure immediately after painting is the usual window.

Access. Someone has to be able to get into the room with the walls finished and nothing stored in it. On a busy site this is harder to arrange than it sounds.

Authority. Somebody has to sign off that the room will not change after the measure. If a wall is still being moved, the measure is worthless.

On a new build, confirm that a check measure is included rather than assuming it. A quote based on plan dimensions alone, with no site measure, is a quote with a risk in it, and the risk usually lands on the owner.

What does the builder need to provide?

For a joinery installation to go well, the room needs to be in a reasonable state. Worth agreeing in writing on a new build.

•            Walls lined, set and painted, to the standard the contract specifies

•            Walls reasonably plumb and square, within normal building tolerance. A wall out beyond tolerance is a building issue, not something for the joiner to absorb by scribing

•            Floors reasonably level, particularly where sliding doors are involved, since a sliding track needs a level run

•            Electrical complete on the wardrobe wall, including any relocations and any power for lighting

•            Set-out confirmed, including where a bulkhead, a cornice or a set-down lands

•            Clear access to the room, and somewhere to bring panels in. On a first floor with a narrow stair, this is a real constraint

•            Protection of finished surfaces

•            Power on site for installation

Where the wardrobe is a builder’s inclusion, most of this is internal to their program. Where the owner has contracted directly with a joinery company, these become coordination points, and they are the ones that get missed.

Builder’s standard, upgrade, or separate contract?

The three options on a new build, with the trade-offs stated plainly.

Builder’s standard inclusion. The wardrobe is in the contract. Simplest, with one party responsible and everything sequenced inside their program. The limitation is specification: standard inclusions are specified to a price point across many homes, and the internal layout is generic rather than built around what you own.

Upgrade through the builder. You keep the single point of responsibility and get a better specification. Usually priced through the builder, so it carries their margin, and the range of what is available is whatever their supplier offers.

Separate contract after handover. Most control over specification, finish and layout. The trade-offs are that you coordinate the timing yourself, the work happens after you have moved in, and anything that needed to happen at rough-in, particularly wardrobe lighting and power, has either already been done or is now a much bigger job.

The common and reasonable middle path: take the builder’s standard provision for secondary bedrooms, and do the main bedroom, walk-in or home office separately to a higher specification. If you plan to do that, raise the rough-in requirements with the builder early, even though the joinery contract comes later. That one conversation is the difference between lighting being possible and not.

How does the sequence differ on a renovation?

Most of the same logic, compressed, with two differences that matter.

The house is occupied. Dust, access and the order in which rooms become unusable all matter in a way they do not on a building site. Wardrobe installation in an occupied home is usually a single-room disruption, but the room is out of use while it happens and the clothes have to be somewhere.

The existing conditions are unknown until something comes out. A new build has a known wall. A renovation has a wall that turns out not to be plumb, a floor that falls, or a redundant bulkhead nobody knew was there. This is normal, and it is the reason a renovation quote is more likely to carry conditions than a new build quote.

The sequence on a renovation runs: strip out the old wardrobe, make good the wall and ceiling, any electrical relocation, paint, hard flooring if it is being replaced, check measure, install, then carpet. The check measure still belongs after painting, for the same reason.

The decision that most often gets made too late on a renovation is the electrical one. If a power point or switch is on the wardrobe wall, or lighting is wanted, it has to be dealt with before the painter, not after the joiner.

Apartments and multi-unit projects

Two additional constraints on top of everything above.

Building access. Lift bookings, protected lift linings, permitted working hours, loading dock access and parking all have to be arranged in advance. On a strata building this is a scheduling problem as much as a trade problem, and lift dimensions can be a genuine design input where panels are large.

Repetition is not uniformity. On a multi-unit project, the temptation is to measure one apartment and apply the dimension across the floor. Units vary, and a dimension applied across forty dwellings produces forty of the same error. Check measures should be taken per dwelling, or at minimum per type with a sample verification across the run, and that should be agreed in the contract rather than assumed.

Where the wardrobes are part of the base build, the same rough-in deadline applies and it applies at scale. Lighting and power decisions made after rough-in across a multi-unit project are not retrofittable at reasonable cost.

For owners buying off the plan, the practical point is that the wardrobe specification is set by the developer and the window to influence it, if there is one at all, closes early. If storage matters to you, ask what the inclusion actually is before exchange, because the difference between a standard inclusion and a designed wardrobe is mostly internal and does not show on a brochure.

Common failures on new builds

Ranked by how often they happen rather than by how serious they are.

Measuring before the walls are finished. The single most common cause of a wardrobe that does not fit.

Lighting decided after rough-in. Then either abandoned or retrofitted visibly.

A switch or outlet left on the wardrobe wall. Buildable around, but it compromises the layout for the life of the house.

Flooring sequence never agreed. Each trade assumes the other is handling it.

Door swings not checked against the room. A hinged wardrobe door and a bedroom door opening into the same corner is a plan-stage error that nobody notices until both are installed.

Ceiling height assumed rather than measured, particularly where a bulkhead or set-down runs along the wardrobe wall.

No single party responsible for the handover between trades. The electrician finished, the painter finished, and nobody told the joiner the room was ready.

Multi-unit projects where one apartment is measured and the dimension is applied to all of them. Units vary. They should not, and they do.

Who coordinates the handover between trades?

The failure that causes more wardrobe problems on a new build than any technical issue, and it is purely administrative.

The painter finishes. The joinery is ready to measure. Nobody tells the joiner. Two weeks later somebody notices, the check measure happens late, manufacture pushes the installation past the carpet layer, and the carpet goes down first because the carpet layer was booked and could not be moved.

The fix is to name a person rather than a process. On a builder-managed job that is the site supervisor. On an owner-managed job with a separate joinery contract, it is the owner, whether they expected it or not.

Three handover points to confirm explicitly:

•            Painter to joiner. Who tells the joinery company the room is ready to measure, and how.

•            Electrician to joiner. Confirmation that all electrical work on the wardrobe wall is complete, including anything relocated.

•            Joiner to floor layer. Confirmation that the joinery is in, so carpet can be laid up to it.

Each of these is a two-line email. Each of them, missed, costs a week.

Handover and defects

Two practical points.

Inspect the joinery at handover specifically, rather than as part of a general walk-through. Open and close every door. Check that doors sit square and align with each other, that drawers run smoothly and close fully, that shelves are level, that scribes to the wall are tight, and that the finish is undamaged at corners and along the base.

Know who is responsible for what. If the wardrobe was a builder’s inclusion, defects go through the builder’s defects process. If you contracted directly, they go to the joinery company. Where a wardrobe was installed by one party and damaged by another working after them, establish that at the time rather than later.

Doors settling slightly in the months after installation is normal, particularly in a new building where the structure is still drying out. Adjustment is ordinary. A door that has dropped noticeably is worth raising rather than living with.

The next step

If you are building, the useful thing is to have the wardrobe conversation early, well before the installation itself, because the decisions that constrain the result are made at rough-in. Impressive Wardrobes offers a free measure and quote, which on a new build is as much a planning conversation as a pricing one.

Book your free measure and quote, or call (02) 9796 1022. If you are a builder or developer working on multiple dwellings, call to discuss how the work fits your program. The showroom is at 54 Canterbury Rd, Bankstown.